4mm Llanfair ....

LarryG

Western Thunderer
The track needs to be sprayed with Howes Sleeper Grime to make an impression on the baseboard, then glued & ballasted down in convenient sections. I didn't have a catchpoint for the coal siding, so a point was used. Empty coal wagons could be pushed by hand into that short stub.....
WEB Track new 3A.jpg

Update : Bullhead track with flat bottom points below. All flat-bottom in picture above. Sprayed Howes Sleeper Grime....
WEB Track new 4A.jpg
 
Last edited:

LarryG

Western Thunderer
The two sunny days we had at the beginning of the week were too hot for gluing down track using the glue & ballast in one go method. Since then, we've had more than a months rainfall in two days in North Wales. I've noticed water on the railway baseboard via a split roofing board, but there is no chance of investigation yet.
 

Richard Gawler

Western Thunderer
I've just done a test area using Ballast Magic. This is a powdered glue you mix with the ballast and set off with a mist of water. My result wasn't strong enough for a permanent installation, but it was strong enough to stay put while I added a dribble of diluted pva. The result has set rock hard so good for a siding, less so for a main line.
 

LarryG

Western Thunderer
Track laying today at long last after months of messing about.....
WEB Track new 5A.jpg

Track laid aside while neat PVA brushed onto baseboard....
WEB Track new 5F.jpg

Track laid and ballasted before noon.....
WEB Track new 5B.jpg

All done by late afternoon....
WEB Track new 5C.jpg

Buildings in place just to see how things looked.....
WEB Track new 5D.jpg

Ballast was a mix of fine light grey and fine dark brown to give a speckled finish.....
WEB Track new 5E.jpg
 

LarryG

Western Thunderer
Please Larry, are you using the PVA neat to do this or are you adding something into it to help it percolate upwards?
It's neat PVA, and the best I've found yet. It is applied thickly with a soft 3/4" brush. Track is lowered onto it and straightened with 3' steel ruler, then ballast poured on. It is firmly tamped with the fingers and hand for a while and the track re-checked in case it had moved. Then strips of 3" x 1" timbers placed on the track with heavy books on top.

Only after the lot is dry do I vacuum off the surplus ballast. This way, the PVA has time to peculate and attach a thicker layer of ballast.
 

Richard Gawler

Western Thunderer
Thanks Larry. A few years ago I had a go in a children's workshop run by Mrs Gravett. I soon learnt I was spreading my pva far too meanly. I don't quite know where it all goes, but it pays to be generous. I still have my sample weeds somewhere.
 

LarryG

Western Thunderer
The compressor and rarely used Airbrush were set up in the railway shed today. There then followed a dismantling session, which failed to make the Airbrush function. I've had three of these toys and they WILL stop working! So the job of weathering the track with rust washed down from rails to ballast was done with the trusty spraygun...

WEB Track new 6.jpg
 

LarryG

Western Thunderer
Been offline for a few days changing the workroom around to suit a new digital BT connection, but it is better for it and the internet is much faster. I made the trap point last week before realising it should have been a complete turnout in that situation! Ah well, all good practice......

WEB Track new 7B.jpg
 
Top